首页Home>资讯详情Item Detail>从建成到投运:绿氢项目卡在电解槽的负荷率上

从建成到投运:绿氢项目卡在电解槽的负荷率上From Construction to Operation: Green Hydrogen Projects Stuck at the Load Factor of Electrolyzers

资讯详情Item Detail绿氢与氢基燃料 | 2026-10-22
信息来源:Source:中国能源产业发展网China Energy Industry Development Network
从建成到投运:绿氢项目卡在电解槽的负荷率上

马行川

在西北的戈壁滩上,风机和光伏板已经立起来,电解槽也装进了厂房,可项目投产后真正的考验才刚开始:设备能不能连续跑、跑在多少负荷上、每一度电的成本能不能算得过账。绿氢产业的规模扩张,正卡在从“建成”到“投运”的最后一段路上——设备调试只是表象,背后是电源、认证与订单三笔账。

140万吨、27万吨、113万吨。三个数字放在一起,是当下绿氢产业最真实的一张剖面图。国家能源局《中国氢能发展报告(2026)》显示,截至2026年6月,我国建成在建可再生能源制氢产能规模超过140万吨/年,其中建成投运超过27万吨/年,在建超过113万吨/年。在建与建成之比约为4.2比1,产能的“堰塞湖”不在图纸上,而在投产这一段。

把时间轴拉开看,变化更快。截至2026年3月底,全国建成在建可再生能源制氢产能超过100万吨/年,建成投运超过25万吨/年,在建超过90万吨/年。三个月时间,在建规模增加约23万吨,投运规模只增加约2万吨。项目开工的速度,明显快于项目开车的速度。

区域分布把矛盾摆得更清楚。已投运产能中,东北地区占45.7%,华北地区占30%,西北地区占21.8%,其余地区合计约2.5%。2025年,东北、华北是主要增长区,新增产能分别超过10万吨/年和2万吨/年。资源最好的地方,往往也是负荷最轻的地方。

绿氢的成本结构决定了这件事的难度。电解水制氢的成本里,电力占大头,设备折旧其次。三北地区的绿电便宜,但风光出力有波动,电解槽要连续稳定运行,就得靠电网兜底或配储平抑。并网运行意味着用网电就要承担输配电价和系统费用,离网运行意味着要靠储能把曲线拉平,两条路都要在成本表上多记一笔。

设备端的账同样不好看。以液氢装备企业国富氢能为例,其2026年中期业绩显示,上半年总收益约1.04亿元,同比减少约4.5%,公司拥有人应占亏损约1.2亿元,上年同期亏损约8920万元。装备卖得出去,利润还没跟上,这是绿氢链条上多数环节的共同处境。

下游的胃口正在打开,但还撑不起140万吨的产能。2025年,全国推广燃料电池汽车近8000辆,氢基燃料船舶累计投运超过10艘,累计发布或试飞氢动力无人机超过30款。工业端的绿氨、绿甲醇建成投运产能分别达到70万吨/年和38万吨/年。这些数字放在一起,说明氢的消纳仍以化工和交通示范为主,规模化工业替代还在爬坡。

基础设施的短板更直观。截至2026年6月,全国累计建成加氢站约620座,建成投运纯氢管道长度超过350公里。140万吨的年产能,对应的是一张仍在铺设的输送网络。氢的运输半径短、储运成本高,管道不通、液氢产能不足,产能就只能停在园区门口。

电价机制是第一个卡口。2025年的650号文允许新能源自建线路向单一用户直供,2026年5月的688号文把范围扩大到多用户,明确工业园区、零碳园区、增量配电网可就近接入新能源,并优先支持算力设施、绿色氢氨醇开展绿电直连。政策给了通道,但项目要算清自发自用比例、输配电价、系统备用费这几笔账,才不会在结算时发现“便宜的绿电”并不便宜。

第二个卡口在认证。欧盟碳边境调节机制自2026年起进入正式征收阶段,出口型化工、钢铁、铝产品要按碳足迹缴费。绿氢、绿氨要卖出溢价,必须拿出可追溯的绿电来源、生产时段和碳排放核算。国内绿氢认证体系仍在建设中,项目从投产到拿到国际认可的绿证,中间还有一段路。

第三个卡口在长协。绿氨、绿甲醇的买家集中在日韩和欧洲,签约周期长、议价能力强。没有十年期的购销协议,银行不敢给项目放长期贷款;没有贷款,项目就只能靠自有资金滚动。国富氢能与韩国Hylium签署的每年1万吨绿氢购销意向协议,之所以被行业反复提及,正是因为它 simultaneously 解决了“卖给谁”和“钱从哪来”两个问题。

把三条卡口合起来看,140万吨的在建规模并不是虚火,它对应的是2027年至2028年集中投产的窗口。真正需要回答的问题是:这些产能投产时,电从哪来、氢往哪去、碳怎么算、钱怎么回。四个问题里只要有一个没答案,项目就会停在“建成未投运”的状态里。

从“建成”到“投运”,中间隔着的不是设备调试,而是商业闭环。2026年到2027年,绿氢产业的竞争焦点会从“谁签的项目多”转向“谁的车开得满”。开车率,将成为比产能规模更硬的指标。

项目业主的结构,也在影响投产节奏。绿氢项目的投资方以能源央企、地方国企和大型化工企业为主,民营企业多集中在装备与工程环节。央企考核看装机与投资完成率,地方看产值与税收,两套考核都指向“开工”,而开车率、负荷率、毛利,往往要等到项目进入运营期才被纳入视线。

电解槽的交付周期是另一个变量。一套大型碱性电解槽从下单到交付通常需要数月,PEM设备更长。设备到场只是第一步,安装、调试、试车、验收,每一步都可能因为配套的电、水、储氢、并网条件不齐而延后。行业里“建成”与“投运”之间隔着半年到一年,并不罕见。

绿证的核发与溯源,决定了绿氢能不能卖出溢价。国际买家要求的是可追溯的绿电来源、明确的时间匹配和碳排放核算方法,国内绿证与绿氢认证的衔接仍在完善。项目即使开车,拿不到被认可的绿色属性证明,产品也只能按普通氢销售。

从投资节奏看,2026年二季度的在建规模比一季度末增加约23万吨,这个增量相当于2025年全年的投运总量。项目储备是充足的,问题在于配套。一个绿氢项目要同时具备电源、土地、水源、氢储运条件和下游协议,缺一项就会拖住整个工期。

地方招商的热度也值得警惕。部分市县把绿氢项目当作招商名片,签约时承诺土地与电价,落地时发现电网接入排队、指标难批。项目名义上开工,实际进展缓慢,最终体现为在建规模大、投运规模小。这种“纸面开工”,是投产率偏低的原因之一。

从产业成熟度看,绿氢仍处在从示范到商业化的过渡期。设备的可靠性、系统的集成能力、运维的经验,都需要项目一个个跑出来。投产率低不完全是坏事,它提醒行业:规模扩张之前,先把第一批项目跑满负荷,把成本和数据跑出来。

对电解槽企业而言,这组数字的另一面是订单结构。在建的113万吨产能,对应的是未来一年多的设备交付;投运的27万吨,对应的是运维、备件与耗材市场。设备商希望在建规模持续放大,运营商希望投运规模尽快上来,两种诉求并不总是同向。

【文中信息及数据来源于:国家能源局《中国氢能发展报告(2026)》、国家能源局2026年4月27日新闻发布会文字实录、国富氢能2026年中期业绩公开披露、国家发展改革委与国家能源局发改能源〔2026〕688号文、公开行业报道】

【研究支持机构:《中国工业报社》能源与双碳研究中心 |中国能源产业发展网】

本文参考数据来源:公开行业报道、国家能源局《中国氢能发展报告(2026)》、国家能源局2026年4月27日新闻发布会实录、国家发展改革委与国家能源局发改能源〔2026〕688号文、国富氢能2026年中期业绩

Ma Xingchuan

On the Gobi Desert in the northwest, wind turbines and photovoltaic panels have already been erected, and electrolyzers have been installed in the plant, but the real test only begins after the project starts production: whether the equipment can run continuously, at what load it can operate, and whether the cost per kilowatt-hour can be accounted for. The scale expansion of the green hydrogen industry is currently stuck in the final stretch from "construction completed" to "operation" — equipment commissioning is just the surface, behind which are three accounts: power supply, certification, and orders.

1.4 million tons, 270,000 tons, 1.13 million tons. These three numbers together form the most realistic profile of the current green hydrogen industry. The National Energy Administration's "China Hydrogen Development Report (2026)" shows that as of June 2026, China has built and is building renewable energy hydrogen production capacity exceeding 1.4 million tons per year, of which more than 270,000 tons per year have been completed and put into operation, and more than 1.13 million tons per year are under construction. The ratio of under-construction to completed is about 4.2 to 1, and the "reservoir" of capacity is not on the blueprint, but in the phase of putting into production.

Looking at the timeline, changes are happening faster. By the end of March 2026, the country will have more than 1 million tons per year of operational and under-construction renewable energy hydrogen production capacity, with over 250,000 tons per year already completed and operational, and over 900,000 tons per year under construction. In three months, the scale under construction increased by about 230,000 tons, while the operational scale only increased by about 20,000 tons. The speed of project commencement is clearly faster than the speed of project commissioning.

The regional distribution makes the contradictions clearer. Among the operational capacity, the Northeast region accounts for 45.7%, North China 30%, Northwest China 21.8%, and the remaining regions combined about 2.5%. In 2025, the Northeast and North China were the main growth areas, with new capacity exceeding 100,000 tons per year and 20,000 tons per year, respectively. The places with the best resources are often also the places with the lightest load.

The cost structure of green hydrogen determines the difficulty of this matter. In the cost of producing hydrogen through water electrolysis, electricity accounts for the largest share, followed by equipment depreciation. Green electricity is cheap in the Three North regions, but wind and solar output fluctuate. Electrolyzers need to operate continuously and stably, which requires either the grid to provide backup or storage to smooth the supply. Connecting to the grid means paying transmission and distribution fees and system charges when using grid electricity, while off-grid operation means relying on energy storage to flatten the curve; both approaches require adding costs on the balance sheet.

The equipment side of the accounting looks just as unappealing. Take the liquid hydrogen equipment company Guofu Hydrogen Energy as an example. Its mid-2026 performance shows that in the first half of the year, total revenue was about 104 million yuan, down about 4.5% year-on-year, and the loss attributable to the company's owners was about 120 million yuan, compared to a loss of about 89.2 million yuan in the same period the previous year. While equipment can be sold, profits have yet to catch up, which is a common situation across most segments of the green hydrogen chain.

Downstream demand is starting to open up, but it is still not enough to support a production capacity of 1.4 million tons. By 2025, nearly 8,000 fuel cell vehicles will be promoted nationwide, more than 10 hydrogen-based ships will be put into operation cumulatively, and over 30 models of hydrogen-powered drones will be released or tested. On the industrial side, the operational capacities of green ammonia and green methanol will reach 700,000 tons/year and 380,000 tons/year, respectively. Taken together, these numbers indicate that hydrogen consumption is still mainly driven by chemical and transportation demonstrations, and large-scale industrial substitution is still on the uphill climb.

The shortcomings in infrastructure are even more evident. As of June 2026, about 620 hydrogen refueling stations have been built nationwide, and over 350 kilometers of pure hydrogen pipelines have been put into operation. An annual production capacity of 1.4 million tons corresponds to a distribution network that is still under construction. With hydrogen’s short transport radius and high storage and transportation costs, without pipelines and sufficient liquid hydrogen production capacity, the output can only stay at the gates of industrial parks.

The electricity pricing mechanism is the first checkpoint. Document No. 650 in 2025 allows renewable energy to build its own lines to supply a single user directly. Document No. 688 in May 2026 expanded the scope to multiple users, clarifying that industrial parks, zero-carbon parks, and incremental distribution networks can connect to renewable energy nearby, and giving priority support for computing facilities and green hydrogen-ammonia-methanol to carry out direct green power connections. The policy provides a channel, but projects need to carefully calculate the proportion of self-use, transmission and distribution fees, and system reserve fees to avoid discovering at settlement time that the 'cheap green power' is actually not cheap.

The second checkpoint is certification. The EU Carbon Border Adjustment Mechanism will enter the official levy stage from 2026, and export-oriented chemical, steel, and aluminum products will have to pay fees based on their carbon footprint. Green hydrogen and green ammonia must be sold at a premium and require traceable sources of green power, production time periods, and carbon emission accounting. The domestic green hydrogen certification system is still under construction, so from project commissioning to obtaining internationally recognized green certificates, there is still a way to go.

The third bottleneck lies in long-term contracts. Buyers of green ammonia and green methanol are concentrated in Japan, South Korea, and Europe, with long signing cycles and strong bargaining power. Without ten-year purchase and sales agreements, banks are reluctant to provide long-term loans for projects; without loans, projects can only rely on self-financing. The reason the yearly 10,000-ton green hydrogen purchase and sales intention agreement signed between Guofu Hydrogen Energy and Korea's Hylium is repeatedly mentioned in the industry is that it simultaneously addresses the questions of "who to sell to" and "where the money comes from."

Looking at the three bottlenecks together, the 1.4 million tons of under-construction capacity is not just hype; it corresponds to the production window concentrated in 2027-2028. The real questions that need answering are: where will the electricity come from when this capacity is put into operation, where will the hydrogen go, how will carbon accounting be done, and how will the money return? If even one of these four questions remains unanswered, the project will remain in a "built but not operational" state.

From 'completion' to 'commissioning,' what lies in between is not equipment debugging, but the commercial closed loop. From 2026 to 2027, the competitive focus of the green hydrogen industry will shift from 'who signs more projects' to 'whose vehicles are running at full capacity.' The operating rate will become a harder metric than production capacity.

The structure of project owners also affects the pace of commissioning. Investors in green hydrogen projects are mainly state-owned energy enterprises, local state-owned enterprises, and large chemical companies, while private companies are mostly concentrated in equipment and engineering sectors. Central enterprises are assessed based on installed capacity and investment completion rate, while local entities focus on output and tax revenue. Both sets of assessments point to 'starting the project,' whereas operating rates, load factors, and gross profit usually only come into view once the project enters the operational phase.

The delivery cycle of electrolyzers is another variable. A set of large alkaline electrolyzers typically requires several months from order to delivery, and PEM equipment takes even longer. Arrival of the equipment is just the first step; installation, commissioning, trial operation, and acceptance can each be delayed due to incomplete supporting conditions such as electricity, water, hydrogen storage, and grid connection. In the industry, it is not uncommon for half a year to a year to elapse between 'completion' and 'commissioning.'

The issuance and traceability of green certificates determine whether green hydrogen can be sold at a premium. International buyers require traceable green electricity sources, clear time matching, and carbon emission accounting methods. The connection between domestic green certificates and green hydrogen certification is still being improved. Even if a project is operational, without recognized proof of its green attributes, the product can only be sold as ordinary hydrogen.

From an investment rhythm perspective, the construction scale in the second quarter of 2026 increased by about 230,000 tons compared to the end of the first quarter, an increment equivalent to the total annual operation volume of 2025. Project reserves are sufficient; the problem lies in supporting facilities. A green hydrogen project must simultaneously have power sources, land, water supply, hydrogen storage and transportation conditions, and downstream agreements; missing any one element can hold up the entire construction period.

The enthusiasm of local investment promotion is also worth being cautious about. Some cities and counties treat green hydrogen projects as promotional tools, making commitments on land and electricity prices when signing agreements, only to discover delays in grid access and difficulty in obtaining approvals. Projects may nominally start construction, but the actual progress is slow, ultimately reflecting a large under-construction scale but a small operational scale. This kind of 'paper start' is one reason for the low production rate.

From the perspective of industry maturity, green hydrogen is still in the transition period from demonstration to commercialization. The reliability of equipment, the system integration capability, and operational experience all need to be developed project by project. Low production rates are not entirely bad; they remind the industry that before expanding scale, the first batch of projects should be run at full capacity to generate costs and data.

For electrolyzer companies, another aspect of these numbers is the order structure. The 1.13 million tons of capacity under construction correspond to equipment deliveries for more than a year; the 270,000 tons in operation correspond to the market for operation, maintenance, spare parts, and consumables. Equipment manufacturers hope that the scale under construction continues to expand, while operators hope that the scale in operation ramps up as quickly as possible. These two demands do not always align.

[Information and data in the text are sourced from: National Energy Administration, China Hydrogen Development Report (2026); transcript of the National Energy Administration press conference on April 27, 2026; Guofu Hydrogen Energy 2026 mid-year performance public disclosure; National Development and Reform Commission and National Energy Administration Document No. 688 (2026); publicly available industry reports]

【Research Supporting Institutions: 'China Industry News' Energy and Dual-Carbon Research Center | China Energy Industry Development Network】

This article's reference data sources: publicly available industry reports, National Energy Administration 'China Hydrogen Energy Development Report (2026)', transcript of the National Energy Administration press conference on April 27, 2026, National Development and Reform Commission and National Energy Administration Document [2026] No. 688 on energy development, Guofu Hydrogen Energy 2026 mid-year performance

版权声明Copyright Notice

本网站摘录或转载的属于第三方的信息,目的在于传递更多信息,内容仅供参考。相关股票、投融资等资讯及分析并不代表本网站赞同其意见和对其真实性负责,不构成投资建议。

若不慎涉及侵权,请在相关内容刊发之日起 30 日内联系我们,我们将第一时间进行删除处理。

转载本网资讯请注明来源作者。本网原创文章、研究报告禁止转发。

Information excerpted or reprinted from third parties on this website is intended to convey more information for reference only. Related stocks, investment and financing news and analysis do not represent the endorsement of this website, nor does this website assume responsibility for their authenticity, and do not constitute investment advice.

If any content unintentionally infringes upon rights, please contact us within 30 days from the date of publication, and we will remove it as soon as possible.

When reprinting content from this website, please indicate the source and author. Original articles and research reports of this website may not be redistributed.

联系电话 / Tel010-85763416邮箱 / EmailEmail / Emaillsrlcyl_2026@163.com
提交询盘留下联系方式,平台将把您的需求推送给匹配的产业方Leave your contact details and we will match you with relevant industry partners.
数据来源与免责声明Data Sources & Disclaimer

数据来源与口径说明:本平台数据与资讯均以「唯一官方口径」采集与发布,优先采用国家部委、国家统计局、海关总署、中国氢能联盟、IEA / IRENA / IMO 等官方或政府间机构公开数据;同一指标只取一个来源,不做多源拼接。数值为公开发布值,可能因统计口径、产地与发布时间不同而存在差异,仅供参考,不构成交易依据。Data sources and methodology: all data and news on this platform are collected and published from a single official source, giving priority to public data from government bodies and intergovernmental organisations such as the National Bureau of Statistics, the General Administration of Customs, the China Hydrogen Alliance, and IEA / IRENA / IMO. One indicator has one source only and is never stitched together from multiple sources. Figures are published values and may vary with statistical scope, origin and release date. For reference only; not a basis for transactions.

AI
智能客服Smart Assistant绿色燃料国际商务网 · 在线服务Green Fuel International Business Network · Online Service
×
人工服务:工作日 09:00—18:00 | 联系电话 010-85763416Human service: Weekdays 09:00—18:00 | Tel 010-85763416
智能客服Smart Assistant